How to Do Installation Qualifications of CNC Machines
Installation qualification (IQ) proves a new machine was delivered, anchored, leveled, powered, and tested to specification before it cuts a production part. This guide is for process engineers and shop leads who own that sign-off. Read it to plan the sequence, set the acceptance numbers, and decide what to reject.

In this article
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
Key takeaways
What IQ covers and what it does not
Installation qualification is the documented proof that a machine was received as ordered, installed as designed, and performs to the acceptance criteria written into the purchase order. It sits between design qualification (DQ), which happens before you buy, and operational qualification (OQ), which proves the machine holds tolerance across its full working envelope and over time. IQ answers a narrower question: is this unit, on this floor, wired and set up the way it is supposed to be?
The deliverable is a signed dossier. It holds the packing list against the PO, the site survey sheet, anchor and leveling records, utility readings, geometric test results, and the test-cut report. If a customer audit or an ISO 9001:2015 surveillance visit lands six months later, that dossier is what you show. Nothing in it should be reconstructed from memory.
IQ does not cover process capability. A machine can pass IQ with a 0.010 mm circularity reading and still be the wrong machine for a job that needs 0.005 mm. That gap belongs to OQ and to the process FMEA. Keep the two documents separate or you will sign off on capability you never measured.
GreatLight runs 127 high-precision CNC machines across three wholly-owned plants, including 16 simultaneous 5-axis machining centers. Every unit goes through the same IQ sequence before it is released to a job. The steps below are the ones we use.
- 1IQ documentOne dossier per machine serial number, signed by the installer and the process engineer.
- 2Who owns itThe process engineer signs acceptance. Maintenance keeps the records.
Site readiness: the checks that fail most often
Pull the foundation drawing from the machine supplier and walk the floor with a level and a tape. Check floor load capacity in kN/m², not just "concrete is thick enough." Check flatness across the footprint, typically 0.05 mm/m or tighter for a 5-axis center. Check vibration isolation if a stamping press or a grinder shares the slab. A machine anchored to a slab that moves will pass IQ in an empty shop and fail three months later.
Verify utilities at the drop point, not at the panel. Electrical: voltage, phase, frequency, and whether the control needs a separate clean earth. Compressed air: pressure at the machine inlet under flow, dew point, and filtration down to 5 μm or better. Coolant: tank location, chip conveyor discharge, and mist extraction route. Network: a live port for program transfer and remote diagnostics.
Confirm the rigging path before the truck arrives. Door clearances, overhead crane capacity, aisle width, and turning radius for the forklift. A 4,000 mm travel machine does not fit through a 2,000 mm door, and unloading it twice costs more than planning the route once.
Cross-check the packing list against the PO line by line when the crates are still sealed. Look for the tool changer, pallet system, coolant unit, chip conveyor, spare parts kit, and the documentation package. Missing documentation is the most common shortfall. Without it you cannot verify parameters or complete the IQ record.
- 1Floor flatness0.05 mm/m across the footprint, or per the supplier drawing if tighter.
- 2Air qualityDry, filtered to 5 μm, pressure stable at the inlet under flow.
Anchoring, leveling, and geometric checks
Set the machine on its leveling pads or anchor bolts, then level the bed in two axes. Use a precision level of 0.02 mm/m resolution. Work corner to corner and re-check after each adjustment, because tightening one pad lifts the opposite corner. On a mill-turn center with a Ø400 mm rotary table, level the table separately from the bed. Target 0.02 mm/m or better; 0.01 mm/m is achievable on a good slab and is worth the extra hour.
Wait 24 hours after anchoring before the final leveling pass. Concrete and castings settle. Re-level, then torque the anchor bolts in a star pattern. Record the final readings with the serial numbers of the level and the square. This is the record an auditor will ask for first.
Run the geometric tests in the order the machine builder specifies. Squareness between X and Y, then X and Z, then spindle axis to the table. Parallelism of the table to the X axis. Spindle runout at the taper gauge line, typically within 0.005 mm. Repeat positioning on each linear axis using a laser interferometer or a ballbar. Backlash should read under 0.005 mm on a new machine.
Take the readings at the middle of travel first, then at both ends. A machine that holds 0.005 mm in the center and 0.015 mm at the end of travel has a geometry problem, not a control problem. Fix it now. It will not get better on its own.
- 1Level target0.02 mm/m or tighter, re-checked 24 hours after anchoring.
- 2Spindle runoutWithin 0.005 mm at the taper gauge line.
Power-up, parameters, and safety verification
Before the first power-up, confirm the supply matches the nameplate: voltage within ±5 %, correct phase rotation, and a ground resistance that meets local code. Phase rotation is worth checking with a meter rather than assuming. A reversed phase on a coolant pump will not damage the machine but will cost you a day.
Load the parameters and the ladder from the documentation package, then compare the backup against the machine serial number. Builders ship parameter sets tuned per unit. Copying a set from a sister machine is a common shortcut that shows up later as servo tuning faults and thermal drift.
Walk the safety chain with the door open and the spindle stopped. Test the door interlock, the emergency stop on the panel and on the pendant, the light curtain if fitted, and the air pressure fault. Every one of these should stop the cycle and require a deliberate reset. Do not accept a reset that happens on power cycling alone.
Back up the parameters, ladder, and servo data to two separate media after the machine is stable. Keep one copy off the machine. The first time a board fails, that backup is the difference between four hours and four days of downtime.
- 1VoltageWithin ±5 % of nameplate, phase rotation confirmed with a meter.
- 2BackupsParameters, ladder, and servo data on two media, one stored off the machine.
Dry run, test cut, and acceptance numbers
Run the warm-up cycle the builder specifies, usually 30 to 60 minutes of spindle and axis motion, before any accuracy test. A cold machine reads differently. Record the ambient temperature and note it on the test sheet. Most acceptance numbers in a purchase order assume a controlled room, typically 20 °C ± 2 °C.
Do a dry run of the acceptance program with the tool clear of the part. Watch the tool changer through a full magazine cycle, the pallet change if fitted, and the coolant and chip conveyor sequence. Listen for a change in pitch on the spindle ramp. A dry run catches programming and interlock faults before they become a crash.
Cut the acceptance part from a material you know. Aluminum 6061 cuts differently from 17-4PH, and a machine tuned on aluminum may show chatter on stainless. Measure the features that matter to the job: bore diameter, flatness, squareness, and surface finish. Write the numbers on the sheet with the tool, the speed, and the feed.
Set the acceptance threshold before the test, not after. If the PO says ±0.005 mm and the machine holds ±0.008 mm on the first pass, that is a fail. Give the builder one chance to re-level and re-tune, then re-test. Accepting a marginal machine because the schedule is tight is how a shop ends up with a machine it cannot use on its best work.
- 1Warm-up30 to 60 minutes of spindle and axis motion before accuracy tests.
- 2ThresholdWritten into the PO before the test cut, not negotiated after.
The IQ sequence, step by step
Run these in order. Skipping a step means redoing the ones after it.
- 11. Verify the site against the foundation drawingCheck floor load, flatness to 0.05 mm/m, vibration sources, and the rigging path. Fix any shortfall before the truck is dispatched, not after.
- 22. Reconcile the delivery against the POOpen the crates with the packing list in hand. Confirm the machine, tool changer, coolant unit, chip conveyor, spares, and the full documentation package.
- 33. Confirm utilities at the drop pointVoltage within ±5 %, phase rotation verified, air dry and filtered to 5 μm, coolant and mist extraction routed, network port live.
- 44. Anchor and level the machineLevel in two axes to 0.02 mm/m or better. Wait 24 hours, re-level, then torque the anchor bolts in a star pattern. Record the level serial number.
- 55. Power up and load parametersMatch the parameter and ladder set to the machine serial number. Do not copy from a sister machine. Back up to two media once stable.
- 66. Run the geometric testsSquareness X-Y and X-Z, spindle axis to table, spindle runout under 0.005 mm, backlash under 0.005 mm. Read at mid-travel and both ends.
- 77. Warm up and dry run30 to 60 minutes of warm-up, then a full dry run with the tool clear. Cycle the tool changer, pallet changer, and chip conveyor.
- 88. Cut the acceptance part and signCut a known material, measure the critical features, and write the numbers against the PO threshold. Both the installer and the process engineer sign.
Typical IQ check items and pass limits
Limits vary by machine class and purchase order. These are the ranges we work to on new 3-axis, 4-axis, and 5-axis centers.
| Check item | Typical pass limit | Instrument | Fail action |
|---|---|---|---|
| Floor flatness | 0.05 mm/m or per drawing | Precision level | Grout or shim before anchoring |
| Bed level | 0.02 mm/m or better | Level, 0.02 mm/m | Re-level, re-check after 24 hours |
| Spindle taper runout | Under 0.005 mm | Dial indicator, 0.001 mm | Reject; do not run production |
| Axis backlash | Under 0.005 mm | Dial indicator | Adjust, re-test, document |
| X-Y squareness | Per PO, typically 0.010 mm/300 mm | Granite square, indicator | Re-level, re-test |
| Repeat positioning | Per PO, laser or ballbar | Laser interferometer | Servo tune, then re-test |
| Air supply | Dry, filtered to 5 μm | Dew point meter, gauge | Fix dryer or filter first |
| Test cut tolerance | ±0.005 mm where specified | CMM or micrometer | One re-tune, then re-test |
A marginal pass is a fail
If the machine misses the threshold written into the purchase order, do not sign. One re-level and re-tune, then re-test. A machine accepted at ±0.008 mm when the job needs ±0.005 mm will cost you far more in scrap and rework than the delay costs now.
Common questions
How long does an IQ take on a new 5-axis center?
Plan on two to three days from unloading to signed dossier for a mid-size 5-axis center, assuming the site is ready and the documentation package is complete. Leveling and the 24-hour settle alone take a day.
Add a day if the machine needs a foundation pour or if the utilities need rework. A machine that arrives before the site is ready costs more in idle rigging time than the extra planning day would have.
Can we do IQ in-house or do we need the builder's engineer?
You can do most of it in-house if you own a precision level, a granite square, indicators, and a way to measure positioning. The builder's engineer is usually required for parameter loading, servo tuning, and the warranty sign-off.
Split it. Your team handles the site survey, anchoring, leveling, utilities, and the test cut. The builder handles parameters and tuning. Both signatures go on the same sheet.
What if the machine fails the test cut?
Give the builder one documented re-level and re-tune, then re-test the same features with the same tool and material. If it still misses the PO threshold, the machine has not been accepted.
Do not release it to production on a verbal promise to fix it later. Get the re-test scheduled in writing before the builder's engineer leaves the site.
Does IQ apply to a used machine as well?
Yes, and it matters more. A used machine carries wear that a new one does not, so the geometric tests and the test cut are the only real evidence of what it will hold.
Set the acceptance limits from the work you intend to run, not from the original spec sheet. A machine that held ±0.005 mm when new may only hold ±0.015 mm now, and that may still be fine for the job.
How does IQ differ from OQ and PQ?
IQ verifies the installation. OQ proves the machine holds tolerance across its full working envelope, at different speeds and materials. PQ proves the process produces a conforming part repeatedly in production conditions.
Keep three separate documents with three separate sign-offs. Merging them is how a shop ends up claiming capability it never measured.
What records should be kept, and for how long?
Keep the packing list, site survey sheet, leveling records with instrument serial numbers, utility readings, geometric test results, parameter backups, and the signed test-cut report.
Retain them for the life of the machine plus the retention period your quality system requires. Under ISO 9001:2015 and IATF 16949:2016, an auditor can ask for the IQ record years after installation.
Need a machine brought online to spec?
Send us the drawing and the tolerance. We quote and return a DFM analysis within 12 hours, and we hold ±0.005 mm on production parts after IQ sign-off.
12-hour quote100% inspectionISO 9001:2015NDA on request