CNC Machining RFQ Guide
An RFQ is not a shopping list. It is a manufacturing plan in disguise. This CNC machining RFQ guide explains what a quote actually prices, which details change the number, and how to tell whether a supplier read your drawing or only your email.

What a CNC Machining RFQ Actually Prices
A request for quotation is a translation step. You hand over a drawing and a quantity, and the shop turns it into time on a machine. Every line in the returned quote maps to a physical action: face the stock, rough the pocket, drill the holes, heat treat, anodize, inspect, pack. If a quote arrives as a single number with no assumptions listed, the shop either guessed or copied a similar job.
The three inputs that move the number are geometry, tolerance and quantity. Geometry sets which machine can reach the part. A bracket with features on five faces needs a 5-axis setup, while a flat plate with a few holes runs on a 3-axis mill in one pass. Tolerance decides how much of the cycle is cutting and how much is measuring. Quantity spreads the setup cost, which is why ten parts often cost far less than ten times one part.
Software turns those inputs into an estimate. CAM software calculates tool paths from the model, applies feeds and speeds for the material, and adds setup time per operation. The shop then overlays real constraints: fixture availability, machine capacity that week, and whether the tolerance can hold on the chosen machine. Two shops can quote the same part 40% apart and both be right, because they planned different processes.
- 1GeometryFace count and feature depth decide the machine.
- 2ToleranceTighter bands add cutting passes and inspection time.
- 3QuantitySetup cost is fixed; cycle time is not.
What to Send With a CNC Machining RFQ
Send a 3D model and a 2D drawing together. The model defines shape; the drawing defines intent. Features that look identical in CAD can carry very different tolerances, and the drawing is where that difference lives. A STEP file alone forces the shop to assume general tolerances, which usually means a looser part than the assembly needs.
On the drawing, call out the datum scheme first. Datums tell the inspector how the part sits in the fixture and in the assembly, so they drive both machining and measurement. Then mark the surfaces that matter: a sealing face at Ra 0.8–1.6 μm, a bearing bore at ±0.005 mm, a clearance hole at ±0.2 mm. Blanket tolerances across every dimension raise the price without improving the part.
Add material grade, surface finish, heat treatment and any secondary operations. Write aluminium 6061-T6, not aluminium. Write anodize hardcoat, not coating. Include thread class, edge break requirements, and whether you need milled radii or a sharp corner. These small words decide which tool the machinist reaches for, and they change the quote.
- 1Model plus drawingSTEP for shape, PDF for tolerance and finish.
- 2Datum schemeSets both fixturing and inspection.
- 3Named materials6061-T6 and 7075 machine differently.
- 4Secondary opsHeat treat, plating and marking add lead time.
How Tolerance and Geometry Pick the Machine
Tolerance and geometry work together to limit the process. A part that fits in a 500 × 500 × 450 mm envelope with features on three faces runs on a 3-axis mill. Add features on the fourth or fifth face and the part must be repositioned for each new setup, unless a 4-axis or 5-axis machine can reach them in one. Every extra setup adds a fixture, a re-datum, and a stack of positional error.
On our floor, 27 three-axis machines handle plate work and simple housings, 12 four-axis mills cover parts that rotate around one axis, and 16 simultaneous 5-axis centers cut complex contours without repositioning. For turned parts, 16 mill-turn centers combine turning and milling in one cycle, which removes a second operation and its re-clamping error. Maximum processing size is 4,000 mm, with travels from 500 × 310 × 200 mm up to 4,000 × 400 × 150 mm.
Tolerance is the second filter. General machining holds ±0.1 mm without effort. Moving to ±0.005 mm changes the plan: finer tools, smaller depth of cut, temperature control, and more frequent in-process checks. That band is achievable on the right machine, but it should be reserved for the two or three dimensions that actually need it. Applying it to the whole part multiplies cost for no gain.
- 1Three-axisFlat parts, one setup, lowest cost.
- 2Four-axisParts rotating around one axis.
- 3Five-axisComplex contours, one setup, no re-datum.
- 4Mill-turnTurned parts with milled features.
Why Two Shops Quote the Same Part Differently
A wide spread between quotes is normal, and it usually comes from process choice rather than margin. One shop plans a single 5-axis setup with a custom soft jaw. Another plans three 3-axis setups with two fixtures. Both can make the part. The first has higher programming and tooling cost, the second has higher labor and positional error. The cheaper quote is not automatically the better one.
Quantity assumptions matter too. A shop quoting 50 pieces will plan a dedicated fixture and amortize it. A shop quoting 10,000 pieces will plan a fixture, a first article, and possibly a second source for raw material. If your RFQ states 50 but your program needs 5,000, ask for both price breaks and note where the process changes.
The third variable is inspection. A general-tolerance part might be checked with calipers. A ±0.005 mm bore needs a coordinate measuring machine and a controlled environment. If the quote does not mention inspection, ask. Unclear inspection scope is the most common source of rejected lots, and the cost lands on both sides.
Finally, watch the material line. Aluminium 7075 and 17-4PH stainless cost more and cut slower than 6061. Titanium and Inconel cut slower still. If two quotes assume different grades, the numbers are not comparable.
- 1Setup strategyOne 5-axis setup versus three 3-axis setups.
- 2Quantity breakThe process plan changes at volume.
- 3Inspection scopeCMM time is a real line item.
How to Read a Quote Back
A usable quote lists assumptions before it lists price. Look for the material grade, the finish specification, the tolerance standard and the inspection method. If the quote says the part will be made to your drawing, confirm that the drawing you sent is the revision referenced. Revision mismatches are a quiet and expensive error.
Then check the lead time breakdown. Quotation and free DFM analysis come back within 12 hours at our shop. Production can start within 24 hours of a released PO. Parts ship in 3–5 days for standard work. If a quote shows a much longer window, ask which step is the bottleneck: material purchase, heat treatment, or machine capacity.
Ask about the NDA if your design is sensitive. Uploads are secure and confidential, and a non-disclosure agreement is available on request. For regulated programs, confirm the quality system: we hold ISO 9001:2015, IATF 16949:2016, ISO 13485:2016 and ISO 27001:2022. Match the certificate to your industry before you release the PO.
One more check: does the quote mention the fixture? For a first run, fixture cost is often the largest single line. Ask whether it is reusable for the next order. If it is, the second order should be cheaper, and a supplier who cannot answer that question has not planned past the first batch.
- 1Assumptions firstThey tell you what is being priced.
- 2Revision matchConfirm the drawing revision in the quote.
- 3Lead time by stepFind the real bottleneck.
- 4Fixture reuseAffects the next order's price.
From RFQ to First Article: The Sequence
Each step has a handoff. A gap at any handoff turns into a change order later.
- 11. Send the packageUpload model, drawing, quantity and target date. State whether the part is a prototype or a production run, because the answer changes the process plan.
- 22. Read the DFM notesA good quote comes back with manufacturability comments: thin walls, deep pockets, tolerances that will not hold, features that need a special tool. These notes are free engineering review.
- 33. Confirm the assumptionsCheck material grade, finish, inspection level and lead time in writing. If the quote says general tolerance and your drawing says ±0.005 mm, resolve it before the PO.
- 44. Release the POOnce assumptions match, production can start within 24 hours. At that point the drawing is frozen; later edits restart setup.
- 55. First article and inspectionThe first part is measured against the datums. Reports are available on request. Approval locks the process for the remaining quantity.
- 66. Production and shippingParts ship in 3–5 days for standard work. 100% inspection before shipment covers raw material, in-process monitoring and final check.
RFQ Detail versus What It Changes
Use this to check whether your request carries enough information to be quoted accurately.
| RFQ detail | If it is missing | What to write instead |
|---|---|---|
| Material grade | Shop assumes a generic alloy | Aluminium 6061-T6, 17-4PH (SUS630) |
| Datum scheme | Tolerance stack is unverifiable | Mark A, B, C on the drawing |
| Critical tolerance | Whole part gets a tight blanket callout | ±0.005 mm on the bearing bore only |
| Surface finish | As-machined finish is assumed | Ra 0.8–1.6 μm on the sealing face |
| Quantity | Setup cost is guessed | 10 prototypes, 5,000 production |
| Finish and marking | Quote excludes secondary ops | Hardcoat anodize, laser mark 1.5 mm |
| Inspection level | Acceptance criteria are unclear | First article plus reports on request |
The Short Version
If your part is flat and general-tolerance, send a model, a quantity and a date; a three-axis shop will quote it in a day. If it has tight bores, five-face features or a regulated end use, spend the extra hour on datums, finish callouts and inspection scope. The RFQ that carries that detail is the one that comes back without change orders.
Common questions
Can I send a STEP file without a 2D drawing?
Yes, and we will quote it. The model defines geometry, so we can plan the process and give a price.
What we cannot infer is intent. Without a drawing we apply general tolerances and an as-machined finish, which may not match your assembly. For anything with a fit, a seal or a bearing, send a drawing with datums and the two or three dimensions that matter.
How tight a tolerance should I put on a CNC machining RFQ?
Put the tightest callout only where the function needs it. Our floor holds ±0.005 mm on the right machine, and finishes down to Ra 0.2–0.8 μm when required.
Blanket tight tolerances increase cycle time and inspection time on every feature. A part with one ±0.005 mm bore and the rest at ±0.1 mm costs far less than the same part with everything at ±0.005 mm, and it works just as well.
What is the minimum order quantity?
There is no minimum order quantity. We run from one prototype to 10,000+ part runs. The process plan changes between those two cases, so tell us which end you are on.
A single prototype is often machined from billet with no dedicated fixture. A 10,000-part run gets a fixture, a first article and a locked process. Quoting both from the same request is possible; just ask for the two price breaks.
How do you protect my design?
Uploads are secure and confidential, and a non-disclosure agreement is available on request. We do not share customer files or use them in marketing without written permission.
For regulated industries we also work under ISO 9001:2015, IATF 16949:2016, ISO 13485:2016 and ISO 27001:2022, which cover information security as well as quality management.
What lead time should I expect after the RFQ?
Quotation and free DFM analysis come back within 12 hours. Once you release the PO, production can start within 24 hours, and standard parts ship in 3–5 days.
Heat treatment, plating and other secondary operations run on their own schedule and are quoted separately. If your date is fixed, tell us at the RFQ stage so the process plan can be built around it.
Which materials can you quote?
Aluminium grades include 6061, 6061-T6, 2024, 5052, 5083, 6063, 6082, 7075 and ADC12. Stainless covers 303, 304, 316, 316L, 420, 430, 431, 440C and 17-4PH. Steel, copper and brass, titanium, Inconel, magnesium and engineering plastics are also available.
Name the grade in the RFQ. Substituting a look-alike alloy changes both the price and the part's behavior in service.