GreatLight CNC Machining Factory logo
CNC Machining
Rapid Prototyping
Materials
Industries
News
About GL

Get Instant Quote

CNC Knowledge

Multi Process Five Axis Machining for Gas Turbine Hardware

Gas turbine casings, brackets and combustor hardware need more than one setup sequence. This guide shows how we plan a multi process five axis route from raw stock to inspection. It is written for process engineers and buyers who have to judge whether a quote, a fixture plan and a tolerance callout will actually hold in production.

±0.005 mm toleranceØ400 mm rotary table16 simultaneous 5-axis centers100% inspection
Multi process five axis machining of gas turbine engine parts
Short answer first

Key takeaways

Split the route by feature, not by machineGroup bores, flanges and angled pads so each 5-axis setup finishes a closed set of tolerances.
Reference the same datum all the way throughA single A-B-C datum chain keeps bore-to-flange position from drifting between setups.
Leave 0.3–0.5 mm for the finishing passRoughing moves metal fast; the last pass controls the ±0.005 mm callouts and surface finish.
Expect 3–5 days after the first article is approvedOnce the fixture is proven, repeat runs ship fast on our 16 simultaneous 5-axis centers.
Why the route matters

What multi process five axis machining means for turbine hardware

A gas turbine casing is a ring of features that must line up: split-line flanges, bore diameters, dowel holes, mounting pads at compound angles, seal grooves. No single setup reaches all of them. Multi process five axis machining means we plan the order of operations so each feature is cut from a datum that still exists, and so the part is not moved until the tolerances that depend on that setup are finished.

The alternative is a stack of 3-axis setups with re-fixturing between each one. Every re-clamp adds position error. On a 600 mm casing with a ±0.005 mm bore-to-bore callout, three re-clamps can burn the whole tolerance band before the cutter touches metal. Five-axis work cuts the count of setups, and that is where the accuracy comes from.

We run 127 high-precision CNC machines, including 16 simultaneous 5-axis machining centers, 12 four-axis mills, 27 three-axis machines and 16 mill-turn centers. That mix matters for turbine work because a casing may need a 4,000 mm envelope for the roughing operation and a Ø400 mm rotary table for the angled pad finishing. The route picks the machine per operation, not per part.

  • 1
    Rough on the largest machineUp to 4,000 × 400 × 150 mm travel for oversized casing sections.
  • 2
    Finish on simultaneous 5-axisRotary table carries the part; the tool stays normal to the surface.
  • 3
    Turn round features on mill-turnBores and seal diameters held in one chuck instead of two setups.
Materials and stock

Reading the drawing before the first cut

Turbine hardware in our shop usually lands in one of four material groups. Stainless 304, 316 and 17-4PH for casings and brackets that see heat and mild corrosion. Inconel and titanium TC4 (Ti-6Al-4V) for hot-section components. 4130, 4140 and 4340 for structural mounts. Aluminium 6061-T6 and 7075 for test hardware and tooling plates that never see the gas path.

Material choice changes the cutting data, not the route logic. Inconel work-hardens fast, so we keep radial engagement low and never let the tool rub. Titanium moves heat into the cutter, so coolant delivery and feed per tooth get checked before the first pass. On 17-4PH we plan for the heat-treat state: machining in condition H1025 behaves differently from annealing stock.

One thing to settle before quoting: is the blank a casting, a forging or plate? A casting arrives with 3–6 mm of stock variation across the surface, so the first operation has to establish a datum from the casting itself, not from an assumed corner. Forgings are closer but still move after stress relief. Plate is the most predictable and the slowest to buy in thick sections.

  • 1
    Ask for the blank drawingStock condition decides how much the first setup can remove.
  • 2
    Confirm heat-treat statePre-hardened stock cuts differently and may need a stress-relief step.
Fixtures and datums

Building a datum chain that survives three setups

The fixture plan is the real deliverable on a turbine part. We pick one primary datum, usually the largest machined face or the split line, and machine it first so every later setup can locate on it. Secondary datums come from dowel or bolt holes that are drilled in the same operation, not from edges that the cutter might have left with a burr.

For a casing with a Ø400 mm rotary table available, the common pattern is: setup one establishes the split face and two dowel holes; setup two holds the part on that face and finishes the inner bore and flange faces; setup three indexes the rotary table to the compound-angle pads. Three setups, one datum chain.

Soft jaws and dedicated fixtures both work. Soft jaws are faster to make for one or two pieces. Above about ten pieces, a dedicated plate with hardened locating pins pays back because the load/unload time drops and repeatability improves. We keep the fixture drawing with the process sheet so a re-run two years later starts from the same numbers.

Do not let the fixture clamp over a surface that will be finished later. It is a small mistake that shows up as a clamp mark on a sealing face, and it usually means a rework or a scrap decision at final inspection.

  • 1
    One datum, three setupsEvery later setup locates on the first machined face.
  • 2
    Clamp on rough surfaces onlyKeep jaws away from sealing faces and bore walls.
Cutting parameters

Setting feeds and finishes for casing features

Roughing removes the bulk. On stainless we run carbide end mills with a 0.3–0.5 mm finishing allowance left on every tolerance surface. Depth of cut can be aggressive when the setup is rigid; the limiting factor is usually chatter at the top of a thin casing wall, not spindle power. When a wall rings, we reduce radial engagement before touching the feed.

Semi-finishing brings the part to 0.1–0.15 mm of nominal and corrects any distortion the roughing released. This is where a casting that moved during the first cut gets pulled back into shape. Skip it and the finishing pass has to remove uneven stock, which pushes tool pressure around and moves the bore.

Finishing controls the callouts. Bores and seal diameters typically land at Ra 0.8–1.6 μm on our machines; sealing faces that need better go to Ra 0.2–0.8 μm with a dedicated finishing pass. Take light depths, 0.05–0.1 mm, and keep the tool path continuous around the bore. A dwell mark in a seal groove is a leak path later.

Angled pads on the rotary table are cut with the tool normal to the surface. Ball-nose cutters leave scallops that depend on stepover: 0.05 mm stepover on a 6 mm ball gives a finish that usually needs no hand work, 0.2 mm stepover leaves visible ridges. Match stepover to the print finish callout rather than to habit.

  • 1
    Rough: leave 0.3–0.5 mmEnough stock for the semi-finish to correct distortion.
  • 2
    Finish: 0.05–0.1 mm depthLight passes hold bore roundness and finish.
Inspection

Checking the part against the datum, not the machine

Every part is inspected before shipment, and the inspection report follows the same datum chain used in machining. On a turbine casing that means the CMM program is written from the primary face and dowel holes, not from a convenient edge. If the print calls out bore-to-bore position, the report shows that distance, not just the individual bore diameters.

In-process checks catch drift before the finishing pass. We measure the semi-finished bore and the two key pads, compare against nominal, and adjust the wear offset for the finishing operation. On a small batch this takes minutes. On a scrapped casing it costs weeks.

Final inspection covers raw material certification, dimensional report, and surface finish where the print specifies it. Reports go out on request. For turbine work we also record the as-machined condition of any sealing surface so the customer can decide whether a coating step is needed.

  • 1
    CMM from the process datumReports match the setup the machinist actually used.
  • 2
    Offset adjustment before finishingCorrect drift while there is still stock to remove.
How we run it

Six steps from drawing to shipped casing

  • 1
    1. Review the drawing and the blankConfirm material, heat-treat state, stock condition and which features carry the tight callouts. Flag any tolerance that needs more than one setup to reach. This is where a DFM note comes back, usually within 12 hours of the quote request.
  • 2
    2. Build the datum chain and process sheetChoose the primary face, list the operations in order, and assign a machine to each. Roughing on the largest available envelope, finishing on a simultaneous 5-axis center. Mark the finishing allowance on every tolerance surface: 0.3–0.5 mm after roughing, 0.1–0.15 mm after semi-finishing.
  • 3
    3. Cut the first setup and prove the datumMachine the primary face and two dowel holes. Verify flatness and hole position before releasing the part to setup two. If the blank is a casting, check that enough stock remains on all later surfaces.
  • 4
    4. Rough and semi-finish the remaining featuresHold the part on the proven datum. Keep radial engagement low on Inconel and titanium. Watch thin walls for chatter; reduce stepover before reducing feed. Measure the semi-finished bore and key pads, then adjust the finishing offset.
  • 5
    5. Finish bores, flanges and angled padsLight depths, 0.05–0.1 mm. Continuous tool paths around bores. Tool normal to angled pads on the rotary table, with stepover matched to the print finish. Target Ra 0.8–1.6 μm on general surfaces, Ra 0.2–0.8 μm on sealing faces.
  • 6
    6. Inspect, document and shipCMM report from the process datum, surface finish check where specified, raw material cert attached. 100% inspection before shipment. Once the first article is approved, repeat parts normally ship in 3–5 days.
Choosing the route

When to use multi process five axis versus 3-axis setups

Match the route to the feature count and tolerance band

ConditionMulti process five axis3-axis with re-fixturing
Angled pads or compound facesCut in one indexed setupNeeds an angle plate per feature
Bore-to-bore position under ±0.01 mmHeld from one datum chainError stacks across re-clamps
Part size above 1,000 mmRoughing on large-travel machineLimited by table and Z height
One or two simple flat partsOverkill for the setup costFaster and cheaper
Sealing faces needing Ra 0.2–0.8 μmContinuous 5-axis tool pathHard to keep path continuity
Batch of 10+ identical partsDedicated fixture pays backSoft jaws repeated per part

When multi process five axis is the right call

If the part has compound-angle features, a tight bore-to-bore callout, or a sealing face that cannot be re-clamped, route it through multi process five axis machining. If it is a flat bracket with one tolerance and a two-week window, a 3-axis setup is cheaper and just as good.

FAQs

Questions engineers ask before releasing a turbine part

Can you hold ±0.005 mm on a casing that is 600 mm across?

Yes, when the datum chain is planned for it and the finishing operation runs on a simultaneous 5-axis center. The tolerance is a shop-wide capability figure, not a promise on every feature of every drawing.

Features far from the primary datum, or surfaces finished in a second setup, need their own review. Send the print and we will tell you which callouts are routine and which need a fixture change.

What stock condition do you need for a casting?

A casting drawing plus the as-cast model. We need to know the stock variation so the first setup can find enough material on every later surface.

If the casting arrives with less than 1.5 mm of stock on a critical face, say so before quoting. It changes the route and sometimes means the part has to be re-cast.

How do you handle thin walls that chatter?

Reduce radial engagement first, then feed. If the wall still rings, we add a temporary support or change the tool to a smaller diameter with a shorter flute length.

Chatter marks on a casing wall are hard to polish out without losing wall thickness, so we catch it during semi-finishing rather than at final inspection.

Do you machine Inconel and titanium?

Yes. Inconel and TC4 (Ti-6Al-4V) are standard materials for us. Both need lower cutting speeds and attention to heat in the cut.

Tool life is shorter than on stainless, so we quote the operation with that factored in rather than discovering it mid-run.

What lead time should we expect?

Quotation and free DFM analysis come back within 12 hours. Production can start within 24 hours of a released order. After the first article is approved, repeat parts normally ship in 3–5 days.

First-article time depends on fixture build and material availability, so it is quoted per part rather than promised as a flat number.

Can you inspect to our CMM program?

We can run a customer-supplied CMM program when the datum scheme matches the process sheet. If it does not, we will flag the mismatch before the run instead of after.

Reports go out on request and include the raw material certification.

Send the drawing and get a process route back

Upload the print and the blank model. We come back with a quote, a DFM note and the setup sequence within 12 hours.

12-hour quote100% inspectionNo minimum order quantityNDA on request

Follow our shop

More machining notes

We publish setup notes, tooling trials and inspection data from the factory floor.

FacebookTikTokYouTubeLinkedInInstagramThreadsPinterest

Trusted by engineers and manufacturers worldwide

Tesla Ford Motor Company BYD Auto Denso Magna International Boeing Airbus Medtronic KUKA FANUC